Power Plants
Ichigo Kiryu Okuzawa ECO Power Plant 2
Located in Gunma Prefecture north of Tokyo, Ichigo Kiryu Okuzawa ECO Power Plant was built on the site of a former stone quarry leased from Kiryu City. With 5,334 solar panels producing a total output of 1.33 MW, the plant generates enough electricity to power 440 households.
Today's
Power Generation
Power Generation
kWh
Today's
CO2 Reduction
CO2 Reduction
kg-CO2
Acquisition of Thirteen Solar Power Plants (12/01/2016) (926181)
Information
-
Location Gunma Prefecture Area 27,588m² Operation Start Date 2013/09/30 Panel Output 1.33MW Panel Maker Toshiba Inverter Supplier Fuji Electric EPC Contractor Kokko Shisetsu Kogyo -
Regional Overview - ・Culture: former center of silk textile manufacturing
・Architecture: sawtooth-roof textile mills, now used as shops
・Industries: metal, machineryKiryu City Website http://www.city.kiryu.lg.jp/index.html Regional Mascot - Kinopi, Kiryu City’s Mascot
- ・Culture: former center of silk textile manufacturing